Ferry Street Re-paving Project Scheduled to Begin on Monday, August 31st!

As part of PSE&G’s Energy Strong Project, the re-paving of Ferry Street will begin next week – on or about Monday, August 31, 2015. Ironbound District businesses, residents and visitors are being advised of the following components of the work to be done:

  • Milling will begin Thursday, August 27, 2015 and take approximately 4 days.
  • Paving will begin on or about September 2nd or 3rd.
  • Re-striping of the roadway will begin immediately following paving.
  • Approximately 2 weeks later, work will begin to install the imprinted crosswalks.

Re-paving of other streets in the Ironbound District impacted by PSE&G’s Energy Strong Project is expected to begin in the weeks ahead as well. Schedule updates will be provided when they become available.

Additional questions can be directed to the IBID at 973-491-9191973-491-9191 or the City of Newark’s Division of Traffic & Signals at 973-733-3985.

Please plan your travel through the area accordingly. Businesses and restaurants will remain open while the re-paving is underway. Thank you for your patience as this important work on the Ironbound District’s infrastructure is completed.